Content: 30928205054957.doc (306.50 KB)
Uploaded: 28.09.2013

Positive responses: 0
Negative responses: 0

Sold: 4
Refunds: 0

Seller: al_ac
information about the seller and its items

Ask a question

Loyalty discount! If the total amount of your purchases from the seller more than:

$20 the discount is 2%
$50 the discount is 5%
$100 the discount is 10%
$0.96
Task №1. To determine the estimated cost and the estimated cost of the works for laying linoleum on the underlying basis teplozvukoizoliruyuschey thickness of 3.6 mm under the following conditions.



Terms Data in thous. (For option)

1 2 3 4 5 6 7 8 9 10

1. costs

on

materials (M)


2. The basic monthly salary (RFP)


3. The costs of operating the machinery (EM)

56.35



5.42




0.10

84.52



8.13




0.15

90.18



8.63




0.16

95.79



9.24




0.17

101.43



9.76




0.18

107.07



10.30




0.19

112.7



10.84




0.20

118.3



11.3




0.21

123.97



11.92




0.22

129.6



12.47




0.23


This task is recommended to perform on 2.2 "the estimated cost structure." It is necessary to clarify the concept of the estimated cost and the cost of construction, part of the direct costs, the procedure for calculating the value of the overhead of civil works and the procedure for determining the amount of planned savings.

Task № 2. Determine the estimated cost of construction of an auto repair shop under the following conditions.

This task is recommended to perform on 2.2 "the estimated cost structure." It is necessary to clarify the concept of the estimated cost of installation work, the composition of the direct costs, the procedure for calculating the value of the cost of installation and the procedure for determining the value of the planned savings.



Terms Data in thous. (For option)

brick monolith team.

w / w window

(Wooden)

floors

top

finishing

Zem.rab metal.

Konstr Protection page. Konstr.

1 2 3 4 5 6 7 8 9 10

1. The cost of the materials (M)


2.Core

wages (ZPO)


3.Zatraty to operate machines and

mechanisms (EM)


4. Wages serving machines

(PAZ) 193.7




16.8





10.50




4.20 212.60




18.48





11.55




4.62 231.92




20.16





12.6




5.04 251.25




21.84





13.65




5.46 274.78




23.52





14.7




5.88 289.91




25.2





15.75




6.3 309.23




26.88





16.8




6.72 328.56




28.56





17.87




7.14 154.62




13.44





8.40




3.36 173.94




17.84





9.45




3.78

No feedback yet